Ask anyone who has tracked an EPC or road contractor for a few years and they will tell you the order book is only half the story. The other half sits quietly with the company’s bankers: its non-fund based limits, the bank guarantees and letters of credit a contractor needs before it can even sign a contract. No cash leaves the bank when these are issued, yet run out of them and a company with a record order book can find itself unable to take on the next job.
This piece explains what non-fund based limits are, why government works contracts eat so much of them, and how to think about the squeeze with a worked example. The rules quoted come from the RBI’s Non-Fund Based Credit Facilities Directions, 2025 and the Manual for Procurement of Works, 2022 (we used the copy hosted by PEC Chandigarh). The company in the example is made up.
In this article
What Non-Fund Based Limits Actually Are
A normal loan or cash credit line is fund based. The bank hands over money and charges interest on it. A non-fund based (NFB) facility is a promise instead. The bank undertakes to pay someone else if its customer fails to do what it promised. The RBI’s directions open by describing NFB facilities as things like guarantees, letters of credit and co-acceptances, which, in the regulator’s words, facilitate credit intermediation and smooth business transactions.
Three instruments do most of the work:
- Bank guarantee (BG). The RBI directions define a guarantee as a contract to perform the promise, or discharge the liability, of a third person if that person does not perform or defaults, in terms of the Indian Contract Act, 1872. For a contractor, the “third person” is the contractor itself and the beneficiary is usually the government department or client.
- Letter of credit (LC). A bank’s promise to pay a seller once the seller presents documents that match the terms of the credit. Its economic effect is to put a creditworthy bank between buyer and seller, so the seller is relying on the bank rather than on the buyer. Contractors use LCs mainly to buy steel, equipment and imported material on credit.
- Co-acceptance of bills. The RBI defines this as an undertaking to pay the drawer of a bill (the seller) on the due date if the buyer fails to pay.
The bank sanctions a ceiling for all of this, the non-fund based limit, alongside the company’s fund based working capital limit. Every guarantee or LC outstanding uses up part of that ceiling until it expires or is released.
Why a Promise Still Counts as Credit
It is tempting to treat NFB limits as soft, since nobody has borrowed anything. Banks do not see it that way, and neither should we.
The RBI directions require a guarantee to be, in general, irrevocable and unconditional, with a clear mechanism for honouring it without demur when it is invoked. A separate clause says a regulated entity must honour a guarantee as and when it is invoked in line with the guarantee deed, unless a court order restrains it. So the client does not have to prove a loss in court before the bank pays. It invokes, and the bank pays.
Once that happens, the promise turns into a loan. The directions say that once an NFB facility devolves and is converted into a fund based facility, the prudential norms for fund based facilities apply. In plain terms, an invoked guarantee becomes money the contractor owes its bank.
A bank guarantee costs the contractor no interest on the day it is issued, but it can turn into a loan on the day the client invokes it. That is why bankers ration it like credit.
There is also a link between the two kinds of limits. The RBI directions say a regulated entity shall issue an NFB facility only on behalf of a customer that has a funded credit facility from it, with listed exceptions. These include facilities fully secured by eligible financial collateral, cases backed by a no-objection certificate from the lender that gives the fund based facility, and obligors with no fund based facility from any regulated entity in India. So, in general, the bank that gives the guarantee is also the one lending working capital.
How Works Contracts Consume the Limit
Here is where contractors feel it. Under the procurement manual, a single government works contract can call for several guarantees at different stages.
1. Bid security before you win
Bidders must submit bid security, also called earnest money deposit (EMD), with their bids, and a bid without it is rejected as non-responsive. The manual says the amount should generally be between two and five per cent of the estimated value. It can be given in several forms, including a bank guarantee, and normally stays valid for 45 days beyond the final bid validity period. Bid security of unsuccessful bidders should be returned at the latest by the 30th day after the contract is awarded, and the winner’s is refunded once it submits performance security.
The point for an investor: a contractor bidding aggressively has guarantees outstanding on jobs it may never win.
2. Performance security after you win
The winning bidder then gives performance security, or a performance bank guarantee (PBG). The manual puts it at five to ten per cent of the contract value and says that in works contracts it is usual to take five per cent. It is generally due 21 days after the award is notified and must stay valid for 60 days beyond the completion of all contractual obligations, including the defect liability period. That last bit matters. A performance guarantee can outlive the construction phase by a long way, so it keeps occupying the limit after the revenue has been booked.
For context, the manual also records a temporary cut: during COVID-19, performance security was reduced to three per cent for existing contracts and for tenders issued or concluded till 31.03.2023.
3. Mobilisation advance
For some specialised and capital intensive works, the manual allows an interest-bearing mobilisation advance of 10 per cent of the contract price, paid against an unconditional bank guarantee. It can be paid in two instalments of five per cent each, the second after the engineer certifies financial progress of 10 per cent of the contract price, with a guarantee for each part. The guarantee amount reduces as the contractor repays the advance. We covered the cash side of this in our explainer on mobilisation advance.
One small line in the manual tells you that guarantees are not free: it says mobilisation expenditure does not include the margin money and bank commission the contractor pays to get guarantees for performance security and mobilisation advance.
4. Retention money swapped for guarantees
Works contracts usually withhold a percentage, usually five per cent, of each running bill as security deposit or retention money until final acceptance. The manual lets the contractor, at its option, replace the retained cash with an unconditional bank guarantee at specified stages. That swap releases cash but uses NFB limit. Our post on retention money goes into the withheld cash in more detail.
A Worked Example: When the Order Book Outruns the Limit
Take a hypothetical road builder, Contractor A. All figures below are illustrative and do not refer to any real company. Margin and commission rates in particular are assumptions; actual terms are set by each bank’s policy, which the RBI directions say must cover fees, commission, tenor and release of security.
| Item | Amount (₹ crore) |
|---|---|
| Sanctioned non-fund based limit | 600 |
| Already used by guarantees and LCs on running projects | 480 |
| Headroom available | 120 |
Contractor A wins a ₹1,500 crore highway contract. What does it need from the bank in the first few weeks?
- Performance security at the usual five per cent: 5% of ₹1,500 crore = ₹75 crore.
- First instalment of mobilisation advance at five per cent of the contract price: ₹75 crore of cash, against a guarantee of ₹75 crore.
That is ₹150 crore of fresh guarantees against ₹120 crore of headroom. A ₹30 crore gap. The bid security of 2% given earlier (₹30 crore, if the department fixed it at the bottom of the range) comes back once the performance security is in, but that only helps if the bank lets the released amount be reused immediately.
Contractor A now has a few choices, none of them free:
- Skip the advance for now. It gives only the ₹75 crore performance guarantee, which fits, and funds mobilisation from its own cash or working capital loans. Interest cost goes up and operating cash flow looks worse in the next quarter.
- Ask for a bigger limit. The bank will want more collateral or cash margin. Suppose it asks for a 10% cash margin on the new ₹150 crore of guarantees. That is ₹15 crore parked in fixed deposits that the company cannot use. On our restricted cash post we explain why such deposits should not be counted as free cash.
- Wait for older guarantees to be released. That depends on clients returning guarantees on completed jobs, and remember that performance guarantees can run for 60 days beyond the defect liability period.
Commission adds up as well. At an assumed 1% a year, ₹150 crore of guarantees costs ₹1.5 crore annually, before counting the return given up on margin money.
Now add the retention swap. If Contractor A bills ₹400 crore on this project in a year and five per cent is retained, ₹20 crore of cash is held back. Replacing that with a guarantee frees ₹20 crore of cash but needs another ₹20 crore of limit. It is a straight trade between cash and limit.
When a contractor’s order inflow jumps faster than its bank lines, the constraint is rarely demand. It is how many more promises its bankers are willing to sign.
Reading Non-Fund Based Limits in Results
A few habits help when you go through a contractor’s numbers:
- Compare order inflow with limit headroom. If management talks about a big jump in new orders, ask what has happened to sanctioned and utilised non-fund based limits. A company quoting both is giving you a real constraint, not just a pipeline.
- Look for guarantees in the notes. Check the notes to accounts for guarantees given by banks on the company’s behalf and the contingent liabilities section. Our explainer on contingent liabilities covers how to read that note.
- Watch margin money and other bank balances. A rising pile of deposits held as margin often tracks rising guarantees.
- Treat invocation as a red flag. Because an invoked guarantee becomes a fund based exposure, any mention of a client invoking a performance guarantee deserves a hard look at the project, the dispute and the cash impact.
- Read mobilisation advances with their guarantees. A large advance on the liability side usually has a matching guarantee outstanding. Repayment of the advance shrinks both.
If you want this inside a broader routine, our pillar on how to analyse quarterly results of a company walks through the income statement and balance sheet checks that come first.
A Few Things That Often Get Mixed Up
- Non-fund based does not mean non-risk. It means no money moves on day one. The risk is the same credit risk, deferred.
- Not every bank’s guarantee is accepted. The manual says guarantees for bid security or performance security should be issued by a scheduled commercial bank, excluding co-operative banks and regional rural banks, and should be verified with the issuing bank before acceptance.
- Clients do keep track. The manual asks departments to review every month the bank guarantees expiring in the next three months and to seek extensions within validity. A contractor cannot count on a guarantee simply lapsing.
- The new RBI rules are recent. The NFB directions came into force from April 1, 2026, or earlier if a bank chose to, and apply to new facilities and renewals after that date.
The Short Version
Non-fund based limits are the bank’s capacity to sign guarantees and letters of credit for a company. For a contractor, every bid, every award, every mobilisation advance and every retention swap draws on them, and performance guarantees can stay outstanding well after a project is finished. When you see a contractor’s order book swell, the useful follow-up question is simple: does it have the guarantee lines to execute it, and at what cost in margin money and commission?
Disclaimer: This article is for educational purposes only and is not investment advice. Contractor A and all figures in the worked example are illustrative, and margin and commission rates are assumptions, not quoted bank terms. Rules are summarised from the RBI Non-Fund Based Credit Facilities Directions, 2025 and the Manual for Procurement of Works, 2022; individual contracts and bank sanctions can differ, so check the actual documents. Please consult a SEBI-registered investment adviser before making any investment decision.