Read the balance sheet of almost any Indian EPC contractor and you’ll find a line that confuses first-time investors: money the company has clearly earned, booked as revenue, and still not received. A big part of that is retention money, a slice of each bill that the client holds back until the work is finished and proven. For a road builder or a power-transmission company it can add up to a sizeable amount, and it explains why profits and cash flows in this sector so often don’t match.
This guide walks through how retention money works under government works contracts in India, how it shows up in the financial statements, and what we look for when a contractor’s results land. If you’re new to reading results in general, our guide on how to analyse quarterly results of a company is a good place to start.
In this article
What retention money actually is
A construction contract isn’t paid in one go. The contractor raises “running bills” as work progresses, the client’s engineer certifies them, and payment follows. Retention is the bit of each payment that doesn’t arrive. The client keeps it as security that the contractor will finish the job and fix any defects that show up afterwards.
The Finance Ministry’s Department of Expenditure spells this out in its Manual for Procurement of Works (2022). Paragraph 4.13 says works contracts usually provide for a percentage of each running bill, usually five percent, to be withheld as security deposit or retention money until final acceptance. The manual uses “security deposit” and “retention money” for the same thing, so don’t be thrown when a company’s notes use one term and its order disclosures use the other.
Retention is separate from the performance security a contractor gives when it signs the contract. Under paragraph 4.12 of the same manual, performance security should be five to ten percent of the contract value, and five percent is usual in works contracts. So on a typical government job, a contractor can have one guarantee sitting with the client from day one and cash being held back from every bill on top of it.
How retention money gets released
The manual lays out a two-step release. One half of the retention money is released when the taking-over certificate is issued, meaning the client has accepted the completed works. The other half is released on expiry of 365 days after the defect liability period, or on final payment, whichever is earlier, once the engineer certifies it.
Think about what that means in time. A project might take two or three years to build. Then there’s a defect liability period. Only after that does the last half come back. Money withheld from the very first running bill can sit with the client for years.
There’s a way around part of it. The manual lets the contractor, at its option, replace the retention amount with an unconditional bank guarantee at two stages: once the amount reaches half the limit of retention money, and again once it reaches the maximum limit. That frees up cash, but it isn’t free. Bank guarantees eat into the contractor’s non-fund-based credit limits and cost commission, so a company leaning heavily on guarantees has its own constraint.
Retention money is revenue a contractor has already booked but can’t spend yet. In a fast-growing order book, that gap widens before it ever narrows.
The CPWD version: 2.5% of each bill
Rates vary by client. The Central Public Works Department’s General Conditions of Contract 2023 (Clause 1A, Recovery of Security Deposit) lets the government deduct 2.5% of the gross amount of each running and final bill until the deductions add up to a security deposit of 2.5% of the tendered amount of the work. The contractor can instead deposit that security as government securities or fixed deposit receipts.
So the same idea comes with different numbers: the Finance Ministry manual describes a usual 5% retention from running bills, while the CPWD conditions use 2.5% of the tendered amount. Private clients, state agencies and overseas employers set their own terms. That’s why we never assume a rate for a listed company; the contract terms or the company’s own disclosures are the only reliable guide.
A worked example (illustrative numbers)
Let’s take a made-up contractor with a ₹1,000 crore government road contract, retention at 5% of each running bill, and no bank-guarantee swap. These figures are for illustration only and don’t describe any real company.
| Year | Work billed (₹ cr) | Retention held back at 5% (₹ cr) | Cumulative retention (₹ cr) |
|---|---|---|---|
| Year 1 | 300 | 15 | 15 |
| Year 2 | 400 | 20 | 35 |
| Year 3 | 300 | 15 | 50 |
By completion, ₹50 crore (5% of ₹1,000 crore) is sitting with the client. Under the two-step rule, half of it, ₹25 crore, comes back when the taking-over certificate is issued. The other ₹25 crore waits until 365 days after the defect liability period or final payment, whichever is earlier.
Now scale it up. Suppose the same company wins four such projects at staggered stages. Revenue looks smooth and growing, yet every new rupee of billing leaves five paise behind. If the company’s operating margin on the project were, say, 10%, the 5% retention would swallow half of that margin in cash terms until release. The profit and loss statement shows the full margin; the cash flow statement doesn’t.
That’s the core reason we read cash from operations alongside profit for any EPC name. A contractor can report rising profits for years while its operating cash flow lags, and retention is one of the usual suspects, along with unbilled work and slow-paying clients.
Where retention shows up in the financial statements
Indian listed companies follow Ind AS 115, the revenue standard (you can read the text at ca2013.com’s Ind AS 115 page). A few paragraphs matter here.
Contract asset versus receivable. Paragraph 107 says that when an entity performs before the customer pays, or before payment is due, it presents a contract asset, excluding amounts shown as a receivable. Paragraph 105 says any unconditional right to consideration must be shown separately as a receivable. Retention that the contractor can claim only after it clears a condition, such as completing the work or getting through the defect period, has the character of a contract asset rather than a plain receivable. How each company classifies it is a judgement disclosed in its notes, so check the accounting policy instead of assuming.
Impairment. Paragraph 107 also requires contract assets to be assessed for impairment under Ind AS 109, the financial-instruments standard. Retention stuck on a disputed or abandoned project can end up written down, which hits profit long after the revenue was booked.
No interest adjustment, usually. Paragraph 60 requires revenue to be adjusted for the time value of money when payment timing gives either party a significant financing benefit. But paragraph 62(c) says there’s no significant financing component when the difference arises for reasons other than finance, and gives the example of payment terms that protect one party from the other failing to complete its obligations. Retention is exactly that kind of protection, which is why contractors generally don’t discount it.
You’ll often find retention mentioned in the notes on trade receivables or contract assets, sometimes as “retention money” and sometimes buried under “security deposits withheld by customers”. Some companies split current and non-current portions, which gives a rough sense of how much is due beyond a year.
Retention money and working capital
EPC companies are notorious for heavy working capital, and retention is part of the reason. It’s money tied up that the company has to fund some other way: from its own cash, from customer advances, or from borrowing.
Customer advances work in the opposite direction. We covered one of them, the mobilisation advance, separately; it brings cash in early and is recovered from later bills. A contractor collecting mobilisation advances on new orders while retention builds up on old ones can look healthy on cash for a while, then see the picture turn as advances get recovered.
When the gap is funded with debt, leverage creeps up. Watching debt against operating profit, as explained in our piece on net debt to EBITDA, helps spot whether a contractor’s growth is quietly being financed by the bank.
A rising order book is good news only if the company can carry the cash it will lock up along the way.
What we check in an EPC company’s results
Here’s the short list we run through when a contractor reports:
- Retention or security deposit balances in the receivables and contract asset notes, and how fast they’re growing compared with revenue.
- Current versus non-current split, if disclosed. A growing non-current chunk means more money waiting beyond a year.
- Operating cash flow against profit. A persistent gap year after year deserves an explanation in the management commentary.
- Impairment or expected credit loss charges on contract assets, especially tied to disputes or arbitration.
- Bank guarantee usage, where disclosed. Swapping retention for guarantees improves cash but uses up limits needed to bid for new work.
- Client mix. Retention terms and payment habits differ between central agencies, state bodies and private clients, and that changes how quickly cash comes back.
None of these is a red flag on its own. Retention is normal; every contractor carries it. What matters is the trend and whether management explains it. A company that grows retention faster than revenue for several years, without a clear project-completion pipeline to unlock it, is telling you something about how its cash will behave.
The takeaway
Retention money is a small percentage of each bill that becomes a big number across a large order book. Government rules make it predictable: the Finance Ministry’s manual describes a usual 5% withheld from running bills and released in two halves, and CPWD’s conditions use 2.5% of the tendered amount. The accounting makes it visible, if you go to the notes. Read it alongside cash flows, and a contractor’s earnings start to make a lot more sense.
Disclaimer: This article is for educational purposes only and is not investment advice. Figures in the worked example are illustrative. Please consult a SEBI-registered investment adviser before making investment decisions.